| Assessment Year | 2025 |
|---|---|
| Principal Product | Thermoset Components and Powdered Metal Components |
| NAICS | 332117: Powder Metallurgy Part Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
110,000
ft2
|
| Annual Production | 100,000
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $437,635 | 2,814,400 |
kWh
|
$0.16 | |
| Electricity Demand | $176,177 | 7,909 |
kW-mo/yr
|
$22.28 | |
| Electricity Fees | $(-13,247.0) | - |
|
- | |
| Natural Gas | $75,467 | 8,506 |
MMBtu
|
$8.87 | |
| Waste Disposal Costs | |||||
| Water Usage | $3,962 | 865 |
Tgal
|
$4.58 | |
| TOTAL YEARLY COSTS | $679,995 | ||||
| RECOMMENDED SAVINGS* | $132,548 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $532 | $1,911 |
$293
1,889
kWh
|
$239
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $18,321 | $5,200 |
$17,832
114,672
kWh
|
$489
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4226: Use / purchase optimum sized compressor | $26,875 | $26,000 |
$20,433
131,399
kWh
|
$6,443
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $23,962 | $75 |
$23,962
154,098
kWh
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,247 | $3,813 |
$728
4,684
kWh
|
$519
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7261: Install timers and/or thermostats | $1,498 | $4,350 |
$269
1,732
kWh
|
- |
$1,229
-
MMBtu
|
- | - | |
| 07 | 2.7496: Install partitions to reduce size of conditioned space | $1,323 | $3,464 | - | - |
$1,323
-
MMBtu
|
- | - | |
| 08 | 2.8123: Pay utility bills on time | $142 | - | - | - | - | $142 | - | |
| 09 | 2.8121: Apply for tax-free status for energy purchases | $4,506 | - | - | - | - | $4,506 | - | |
| 10 | 2.3212: Optimize plant power factor | $25,429 | $32,020 | - | - | - | $25,429 | - | |
| 11 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,759 | $2,730 |
$8,158
53,465
kWh
|
$1,601
-
kW-mo/yr
|
- | - | - | |
| 12 | 2.3141: Use battery storage for demand control | $6,925 | $26,046 |
$(-2,649.3)
(-17,037)
kWh
|
$16,042
-
kW-mo/yr
|
- | - | $(-6,467.3) | |
| 13 | 2.2511: Insulate bare equipment | $1,209 | $2,300 |
$1,209
7,775
kWh
|
- | - | - | - | |
| 14 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,579 | $1,558 |
$9,579
59,868
kWh
|
- | - | - | - | |
| 15 | 2.7314: Reduce ventilation air | $1,241 | $18,070 |
$848
5,455
kWh
|
$201
-
kW-mo/yr
|
$192
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $132,548 | $127,538 |
$80,662
517,999
kWh
|
$25,533
-
kW-mo/yr
|
$2,743
-
MMBtu
|
$30,076 | $(-6,467.3) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs