ITAC Assessment: TT0201
ITAC logo
ITAC Assessment: TT0201
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Solid Wood Flooring
NAICS 321918: Other Millwork (including Flooring)
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $50
M
to 100
M
# of Employees 219
Plant Area 344,130
ft2
Annual Production 1,680
units
Production Hrs. Annual 4,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $700,159 17,560,408
kWh
Electricity Demand $387,881 36,356
kW-mo/yr
Natural Gas $12,193 1,467
MMBtu
Waste Disposal Costs
Water Usage $3,037 730
Tgal
Water Disposal $4,442 730
Tgal
TOTAL YEARLY COSTS $1,107,712
RECOMMENDED SAVINGS* $602,307 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat $339,254 $1,500,000 $371,424
9,285,600
kWh
$135,722
-
kW-mo/yr
- $(-50,000.0) $(-117,892.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $130,717 $332,125 $84,458
2,114,904
kWh
$23,761
-
kW-mo/yr
- $22,498 -
03 2.2121: Increase amount of condensate returned $36,301 $12,000 - - - - $36,301
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $26,588 $126,000 $26,588
664,686
kWh
- - - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $19,888 $10,000 - - - - $19,888
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $13,682 $26,000 $6,518
162,944
kWh
$7,164
-
kW-mo/yr
- - -
07 2.4321: Upgrade obsolete equipment $12,087 $360 $11,585
289,620
kWh
$502
-
kW-mo/yr
- - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,271 $3,000 $8,271
206,784
kWh
- - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,818 $23,900 $3,529
88,213
kWh
$1,289
-
kW-mo/yr
- - -
10 2.1243: Use heat from boiler blowdown to preheat boiler feed water $3,329 $15,000 - - - - $3,329
11 2.4151: Develop a repair/replace policy $3,298 $8,481 $1,864
46,600
kWh
$1,434
-
kW-mo/yr
- - -
12 2.1121: Use insulation in furnaces to facilitate heating / cooling $2,035 $1,000 - - $2,035
-
MMBtu
- -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,150 $3,500 $1,150
28,741
kWh
- - - -
14 2.4221: Install compressor air intakes in coolest locations $802 $1,700 $567
14,175
kWh
$235
-
kW-mo/yr
- - -
15 2.7261: Install timers and/or thermostats $87 $100 $87
2,176
kWh
- - - -
TOTAL RECOMMENDED $602,307 $2,063,166 $516,041
12,904,443
kWh
$170,107
-
kW-mo/yr
$2,035
-
MMBtu
$(-27,502.0) $(-58,374.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs