Assessment Year | 2017 |
---|---|
Principal Product | Solid Wood Flooring |
NAICS | 321918: Other Millwork (including Flooring) |
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $50 M to 100M |
# of Employees | 219 |
Plant Area |
344,130
ft2
|
Annual Production | 1,680
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $700,159 | 17,560,408 |
kWh
|
$0.040 | |
Electricity Demand | $387,881 | 36,356 |
kW-mo/yr
|
$10.67 | |
Natural Gas | $12,193 | 1,467 |
MMBtu
|
$8.31 | |
Waste Disposal Costs | |||||
Water Usage | $3,037 | 730 |
Tgal
|
$4.16 | |
Water Disposal | $4,442 | 730 |
Tgal
|
$6.08 | |
TOTAL YEARLY COSTS | $1,107,712 | ||||
RECOMMENDED SAVINGS* | $602,307 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $339,254 | $1,500,000 |
$371,424
9,285,600
kWh
|
$135,722
-
kW-mo/yr
|
- | $(-50,000.0) | $(-117,892.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $130,717 | $332,125 |
$84,458
2,114,904
kWh
|
$23,761
-
kW-mo/yr
|
- | $22,498 | - | |
03 | 2.2121: Increase amount of condensate returned | $36,301 | $12,000 | - | - | - | - | $36,301 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,588 | $126,000 |
$26,588
664,686
kWh
|
- | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $19,888 | $10,000 | - | - | - | - | $19,888 | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,682 | $26,000 |
$6,518
162,944
kWh
|
$7,164
-
kW-mo/yr
|
- | - | - | |
07 | 2.4321: Upgrade obsolete equipment | $12,087 | $360 |
$11,585
289,620
kWh
|
$502
-
kW-mo/yr
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,271 | $3,000 |
$8,271
206,784
kWh
|
- | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,818 | $23,900 |
$3,529
88,213
kWh
|
$1,289
-
kW-mo/yr
|
- | - | - | |
10 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $3,329 | $15,000 | - | - | - | - | $3,329 | |
11 | 2.4151: Develop a repair/replace policy | $3,298 | $8,481 |
$1,864
46,600
kWh
|
$1,434
-
kW-mo/yr
|
- | - | - | |
12 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $2,035 | $1,000 | - | - |
$2,035
-
MMBtu
|
- | - | |
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,150 | $3,500 |
$1,150
28,741
kWh
|
- | - | - | - | |
14 | 2.4221: Install compressor air intakes in coolest locations | $802 | $1,700 |
$567
14,175
kWh
|
$235
-
kW-mo/yr
|
- | - | - | |
15 | 2.7261: Install timers and/or thermostats | $87 | $100 |
$87
2,176
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $602,307 | $2,063,166 |
$516,041
12,904,443
kWh
|
$170,107
-
kW-mo/yr
|
$2,035
-
MMBtu
|
$(-27,502.0) | $(-58,374.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs