Assessment Year | 2009 |
---|---|
Principal Product | Hushpuppies |
NAICS | 311412: Frozen Specialty Food Manufacturing |
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 65 |
Plant Area |
100,000
ft2
|
Annual Production | 19,000,000
lb
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $404,505 | 4,234,800 |
kWh
|
$0.096 |
Electricity Demand | $148,321 | 10,950 |
kW-mo/yr
|
$13.55 |
Electricity Fees | $9,036 | - |
|
- |
Natural Gas | $157,898 | 12,925 |
MMBtu
|
$12.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,494 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $34,896 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $5,027 | $5,400 |
$5,027
58,792
kWh
|
- | |
02 | 2.7314: Reduce ventilation air | $3,415 | - |
$3,415
39,940
kWh
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $7,850 | $6,000 | - |
$7,850
-
MMBtu
|
|
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,180 | $2,000 | - |
$4,180
-
MMBtu
|
|
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $13,904 | $30,870 |
$13,904
157,014
kWh
|
- | |
06 | 2.2113: Repair or replace steam traps | $1,748 | $4,000 |
$1,748
19,743
kWh
|
- | |
07 | 2.4227: Use compressor air filters | $323 | $75 |
$323
3,650
kWh
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,476 | $4,900 |
$3,476
39,249
kWh
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,198 | - |
$2,198
24,821
kWh
|
- | |
10 | 2.4151: Develop a repair/replace policy | $373 | $976 |
$373
4,662
kWh
|
- | |
TOTAL RECOMMENDED | $42,494 | $54,221 |
$30,464
347,871
kWh
|
$12,030
-
MMBtu
|
||
TOTAL IMPLEMENTED | $34,896 | $47,845 |
$22,866
259,596
kWh
|
$12,030
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs