ITAC Assessment: TN0695
ITAC logo
ITAC Assessment: TN0695
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Disposable Razors
NAICS
n/a
SIC 3421: Cutlery
Sales Range $50
M
to 100
M
# of Employees 176
Plant Area 140,000
ft2
Annual Production 1,700,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $370,802 11,412,661
kWh
Electricity Demand $211,861 21,459
kW-mo/yr
Natural Gas $6,567 951
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $289,435 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
01 4.421: Modify current incentive program $80,000 $16,690 n/a - - - - - - $80,000 -
02 3.5248: Separate and recycle scrap metal to foundry or for sale $52,800 $320 n/a - - - - $52,800
-
lb
- - -
03 2.4157: Establish a predictive maintenance program $50,645 $5,075 n/a $42,440
1,326,202
kWh
- - - - - - $8,205
04 3.1191: Change procedures / equipment / operating conditions $28,960 $52,400 n/a - - - $28,960
-
gal
- - - -
05 2.3191: Use demand controller or load shedder $26,200 $18,500 n/a - $26,200
-
kW-mo/yr
- - - - - -
06 3.1191: Change procedures / equipment / operating conditions $20,730 $1,175 n/a - - - - $20,730
-
lb
- - -
07 2.2614: Use cooling tower or economizer to replace chiller cooling $15,015 $21,850 n/a $10,675
333,529
kWh
$4,340
-
kW-mo/yr
- - - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $6,245 - n/a $4,210
131,594
kWh
$2,035
-
kW-mo/yr
- - - - - -
09 2.7447: Install vinyl strip / high speed / air curtain doors $3,800 $5,510 n/a $3,650
84,115
kWh
- $150
-
MMBtu
- - - - -
10 2.7144: Install spectral reflectors / delamp $2,880 $1,850 n/a $1,595
48,066
kWh
$1,080
-
kW-mo/yr
- - - $205
-
lb
- -
11 2.7261: Install timers and/or thermostats $2,160 $2,820 n/a $2,160
49,824
kWh
- - - - - - -
TOTAL RECOMMENDED $289,435 $126,190 $64,730
1,973,330
kWh
$33,655
-
kW-mo/yr
$150
-
MMBtu
$28,960
-
gal
$73,530
-
lb
$205
-
lb
$80,000 $8,205
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Administrative Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs