Assessment Year | 1996 |
---|---|
Principal Product | Graduation announcements and cards |
NAICS |
n/a
|
SIC | 2753: |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
87,000
ft2
|
Annual Production | 28,000,000
pieces
|
Production Hrs. Annual | 4,375
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,656 | 1,874,560 |
kWh
|
$0.034 |
Electricity Demand | $44,080 | 5,639 |
kW-mo/yr
|
$7.82 |
Natural Gas | $7,943 | 1,224 |
MMBtu
|
$6.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,574 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,325 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5311: Recover and reuse waste material | $20,100 | $3,160 |
$(-500.0)
(-16,120)
kWh
|
- | - |
$23,600
-
lb
|
$(-3,000.0) | - | - | - | |
02 | 3.1191: Change procedures / equipment / operating conditions | $8,810 | $7,200 |
$(-1,209.0)
(-38,980)
kWh
|
- | - |
$140
-
lb
|
- | $9,900 | - |
$(-21.0)
-
Tgal
|
|
03 | 3.8314: Purchase high materials in returnable bulk containers | $3,040 | $600 | - | - | - |
$690
-
lb
|
- | $2,350 | - | - | |
04 | 2.7226: Use computer programs to optimize hvac performance | $2,820 | $5,440 |
$2,470
79,719
kWh
|
- |
$350
-
MMBtu
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,505 | - |
$291
9,379
kWh
|
$2,484
-
kW-mo/yr
|
- | - | - | - | $(-270.0) | - | |
06 | 3.1111: Cover ink containers when not in use | $1,400 | - | - | - | - |
$1,900
-
lb
|
$(-500.0) | - | - | - | |
07 | 2.7135: Install occupancy sensors | $860 | $1,600 |
$860
27,843
kWh
|
- | - | - | - | - | - | - | |
08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $730 | $1,480 |
$520
16,706
kWh
|
- |
$210
-
MMBtu
|
- | - | - | - | - | |
09 | 2.6232: Install set-back timers | $200 | $435 |
$200
6,448
kWh
|
- | - | - | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $109 | $300 |
$55
1,758
kWh
|
$54
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $40,574 | $20,215 |
$2,687
86,753
kWh
|
$2,538
-
kW-mo/yr
|
$560
-
MMBtu
|
$26,330
-
lb
|
$(-3,500.0) | $12,250 | $(-270.0) |
$(-21.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $5,325 | $5,440 |
$2,761
89,098
kWh
|
$2,484
-
kW-mo/yr
|
$350
-
MMBtu
|
- | - | - | $(-270.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs