ITAC Assessment: TN0582
ITAC logo
ITAC Assessment: TN0582
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Hydraulic valves and components
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 322
Plant Area 150,000
ft2
Annual Production 490,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $391,483 8,989,156
kWh
Electricity Demand $64,786 19,359
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,792 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,637

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 3.5316: Contract a wood pallet recycling company $25,500 - - - - $2,600
-
lb
- - - - $22,900
02 3.5315: Lease / purchase baler; sell cardboard to recycler $18,000 $8,640 - - - $7,700
-
lb
- $(-6,500.0) $16,800 - -
03 3.2121: Convert to electrostatic powder coating $12,600 $26,600 $(-500.0)
(-12,309)
kWh
- - - $1,700
-
lb
$2,800 - - $8,600
04 2.7111: Reduce illumination to minimum necessary levels $12,053 - $10,334
252,052
kWh
$1,719
-
kW-mo/yr
- - - - - - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,032 $23,975 $4,122
100,528
kWh
$4,910
-
kW-mo/yr
- - - - - - -
06 3.6192: Use a less expensive method of waste removal $8,800 - - - - - - - $8,800 - -
07 3.5215: Avoid contamination of end pieces and reuse as feed stock $8,000 $1,500 - - - $(-2,755.0)
-
lb
- $(-7,000.0) - $17,755 -
08 2.7442: Keep doors and windows shut when not on use $6,537 - $6,537
159,437
kWh
- - - - - - - -
09 2.7261: Install timers and/or thermostats $4,206 $16,400 $4,206
102,579
kWh
- - - - - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $4,144 $2,730 $3,244
79,132
kWh
$900
-
kW-mo/yr
- - - - - - -
11 2.4221: Install compressor air intakes in coolest locations $2,800 $360 $2,379
58,030
kWh
$421
-
kW-mo/yr
- - - - - - -
12 3.4113: Treat and reuse rinse waters $1,120 $2,600 $(-100.0)
(-2,345)
kWh
- $860
-
Tgal
- - - - - $360
TOTAL RECOMMENDED $112,792 $82,805 $30,222
737,104
kWh
$7,950
-
kW-mo/yr
$860
-
Tgal
$7,545
-
lb
$1,700
-
lb
$(-10,700.0) $25,600 $17,755 $31,860
TOTAL IMPLEMENTED $69,637 $10,500 $8,916
217,467
kWh
$421
-
kW-mo/yr
- $7,545
-
lb
- $(-13,500.0) $25,600 $17,755 $22,900
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs