Assessment Year | 1994 |
---|---|
Principal Product | Automobile steel tubing |
NAICS |
n/a
|
SIC | 3498: Fabricated Pipe and Pipe Fittings |
Sales Range | $10 M to 50M |
# of Employees | 184 |
Plant Area |
53,000
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 7,650
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,480 | 2,091,735 |
kWh
|
$0.053 |
Natural Gas | $9,973 | 1,302 |
MMBtu
|
$7.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,255 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,901 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,901 | $840 |
$8,901
167,937
kWh
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $4,241 | $620 |
$4,241
79,719
kWh
|
- | |
03 | 2.4314: Use synthetic lubricant | $3,076 | - |
$3,076
58,030
kWh
|
- | |
04 | 2.7261: Install timers and/or thermostats | $997 | $1,100 |
$419
7,913
kWh
|
$578
-
MMBtu
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $450 | $280 |
$450
8,499
kWh
|
- | |
06 | 2.3212: Optimize plant power factor | $5,590 | $6,000 |
$5,590
-
kWh
|
- | |
TOTAL RECOMMENDED | $23,255 | $8,840 |
$22,677
322,098
kWh
|
$578
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,901 | $840 |
$8,901
167,937
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs