Assessment Year | 1989 |
---|---|
Principal Product | FROZEN DOUGH,BAKED GOODS |
NAICS |
n/a
|
SIC | 2045: Prepared Flour Mixes and Doughs |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 100,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $754,063 | 15,238,863 |
kWh
|
$0.049 |
Natural Gas | $130,863 | 36,740 |
MMBtu
|
$3.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,443 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,299 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $4,216 | $560 |
$1,034
21,102
kWh
|
$3,182
-
MMBtu
|
- | |
02 | 2.2511: Insulate bare equipment | $3,071 | $2,300 | - |
$3,071
-
MMBtu
|
- | |
03 | 2.7123: Keep lamps and reflectors clean | $8,857 | $10,432 |
$8,444
172,333
kWh
|
- | $413 | |
04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $7,224 | $10,400 |
$7,224
147,421
kWh
|
- | - | |
05 | 2.2135: Repair and eliminate steam leaks | $1,210 | $380 | - |
$1,210
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,251 | $270 |
$4,251
86,753
kWh
|
- | - | |
07 | 2.6232: Install set-back timers | $3,648 | - |
$3,648
74,443
kWh
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,449 | - |
$1,449
29,308
kWh
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $517 | $301 |
$517
10,551
kWh
|
- | - | |
TOTAL RECOMMENDED | $34,443 | $24,643 |
$26,567
541,911
kWh
|
$7,463
-
MMBtu
|
$413 | ||
TOTAL IMPLEMENTED | $18,299 | $11,351 |
$17,089
348,476
kWh
|
$1,210
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs