ITAC Assessment: TN0319
ITAC logo
ITAC Assessment: TN0319
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product AIRCRAFT LANDING GEAR
NAICS
n/a
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 375
Plant Area
n/a
Annual Production 8,160
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $595,629 13,305,100
kWh
Natural Gas $8,749 1,814
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,592 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,851

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7123: Keep lamps and reflectors clean $20,390 $14,278 $20,390
453,107
kWh
02 2.7251: Reduce air conditioning load by evaporating water from roof $8,283 $25,363 $8,283
184,056
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $15,035 $2,880 $15,035
334,115
kWh
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,706 - $3,706
82,356
kWh
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,556 $240 $1,556
34,584
kWh
06 2.4221: Install compressor air intakes in coolest locations $1,068 $270 $1,068
23,740
kWh
07 2.7442: Keep doors and windows shut when not on use $554 - $554
12,309
kWh
TOTAL RECOMMENDED $50,592 $43,031 $50,592
1,124,267
kWh
TOTAL IMPLEMENTED $20,851 $3,120 $20,851
463,364
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs