ITAC Assessment: TN0309
ITAC logo
ITAC Assessment: TN0309
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product FOAM CARPET UNDERLAY
NAICS
n/a
SIC 2822: Synthetic Rubber (Vulcanizable Elastomers)
Sales Range $5
M
to 10
M
# of Employees 56
Plant Area
n/a
Annual Production 4,800,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,274 1,087,046
kWh
Natural Gas $10,867 2,541
MMBtu
Fuel Oil #2 $8,873 2,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,457 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,962

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $1,793 $2,480 - $1,011
-
MMBtu
$782
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,069 $165 $3,069
54,807
kWh
- -
03 2.6232: Install set-back timers $2,495 - $2,495
44,549
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $558 $470 $558
9,965
kWh
- -
05 2.6218: Turn off equipment when not in use $542 $300 $542
9,672
kWh
- -
TOTAL RECOMMENDED $8,457 $3,415 $6,664
118,993
kWh
$1,011
-
MMBtu
$782
-
MMBtu
TOTAL IMPLEMENTED $5,962 $3,415 $4,169
74,444
kWh
$1,011
-
MMBtu
$782
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs