ITAC Assessment: TN0286
ITAC logo
ITAC Assessment: TN0286
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product GEAR CLAMPS
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 140,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $230,200 5,305,100
kWh
Natural Gas $12,653 2,388
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,604

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7226: Use computer programs to optimize hvac performance $6,868 $2,430 $6,868
159,730
kWh
-
02 2.7261: Install timers and/or thermostats $2,353 $1,315 - $2,353
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,478 - $3,478
80,891
kWh
-
04 2.7243: Improve air circulation with destratification fans / other methods $1,097 $3,500 - $1,097
-
MMBtu
05 2.2447: Heat water with exhaust heat $875 $3,900 - $875
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $1,285 $615 $1,285
29,894
kWh
-
07 2.7447: Install vinyl strip / high speed / air curtain doors $744 $300 $744
17,292
kWh
-
TOTAL RECOMMENDED $16,700 $12,060 $12,375
287,807
kWh
$4,325
-
MMBtu
TOTAL IMPLEMENTED $6,604 $4,415 $5,507
128,077
kWh
$1,097
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs