ITAC Assessment: SU0163
ITAC logo
ITAC Assessment: SU0163
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Precast Concrete
NAICS 327390: Other Concrete Product Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 53
Plant Area 83,111
ft2
Annual Production 80,000
ton
Production Hrs. Annual 3,770
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,984 723,693
kWh
Electricity Demand $45,538 3,279
kW-mo/yr
Electricity Fees $10,401 -
Natural Gas $45,513 7,659
MMBtu
LPG $6,129 611
MMBtu
Other Gas $22,093 2,488
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,119 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,883

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 2.2192: Use heat exchange fluids instead of steam in pipeline tracing systems $7,056 $71,690 - - $7,056
-
MMBtu
02 2.4226: Use / purchase optimum sized compressor $5,236 $43 $5,236
87,270
kWh
- -
03 2.1133: Adjust burners for efficient operation $4,914 $540 - - $4,914
-
MMBtu
04 2.7261: Install timers and/or thermostats $2,900 $236 $429
7,144
kWh
- $2,471
-
MMBtu
05 2.8121: Apply for tax-free status for energy purchases $2,031 - - $2,031 -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,756 - $1,756
29,261
kWh
- -
07 2.7135: Install occupancy sensors $226 $116 $226
3,767
kWh
- -
TOTAL RECOMMENDED $24,119 $72,625 $7,647
127,442
kWh
$2,031 $14,441
-
MMBtu
TOTAL IMPLEMENTED $18,883 $72,582 $2,411
40,172
kWh
$2,031 $14,441
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs