Assessment Year | 2018 |
---|---|
Principal Product | Adhesives |
NAICS | 325520: Adhesive Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 26 |
Plant Area |
100,000
ft2
|
Annual Production | 8,000,000
lb
|
Production Hrs. Annual | 3,125
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,946 | 926,520 |
kWh
|
$0.069 |
Electricity Demand | $10,051 | 1,491 |
kW-mo/yr
|
$6.74 |
Electricity Fees | $8,711 | - |
|
- |
Natural Gas | $38,308 | 6,658 |
MMBtu
|
$5.75 |
TOTAL YEARLY COSTS | $121,016 | |||
RECOMMENDED SAVINGS* | $11,939 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,639 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,647 | $16,472 |
$2,874
41,655
kWh
|
$1,773
-
kW-mo/yr
|
- | |
02 | 2.7134: Use photocell controls | $1,341 | $450 |
$1,058
15,330
kWh
|
$283
-
kW-mo/yr
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $352 | $90 | - | - |
$352
-
MMBtu
|
|
04 | 2.4226: Use / purchase optimum sized compressor | $4,137 | $12,000 |
$3,009
43,602
kWh
|
$1,128
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $300 | $1,250 | - | - |
$300
-
MMBtu
|
|
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,162 | $50,000 | - | - |
$1,162
-
MMBtu
|
|
TOTAL RECOMMENDED | $11,939 | $80,262 |
$6,941
100,587
kWh
|
$3,184
-
kW-mo/yr
|
$1,814
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,639 | $79,012 |
$6,941
100,587
kWh
|
$3,184
-
kW-mo/yr
|
$1,514
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs