Assessment Year | 1985 |
---|---|
Principal Product | METAL DOORS |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $5 M to 10M |
# of Employees | 295 |
Plant Area |
n/a
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 4,817
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,189 | 1,932,005 |
kWh
|
$0.088 |
Natural Gas | $130,655 | 21,849 |
MMBtu
|
$5.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,977 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,137 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,127 | $2,011 |
$8,127
92,321
kWh
|
- | |
02 | 2.2437: Recover waste heat from equipment | $4,934 | $500 | - |
$4,934
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $722 | $85 |
$722
8,206
kWh
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,504 | $537 | - |
$2,504
-
MMBtu
|
|
05 | 2.1123: Install automatic stack damper | $3,141 | $6,344 | - |
$3,141
-
MMBtu
|
|
06 | 2.2443: Re-use or recycle hot or cold process exhaust air | $2,403 | $6,000 | - |
$2,403
-
MMBtu
|
|
07 | 2.6121: Reduce hot water temperature to the minimum required | $527 | - | - |
$527
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,305 | $200 |
$20,305
230,657
kWh
|
- | |
09 | 2.7441: Replace broken windows and/or window sash | $2,840 | $23 |
$232
2,638
kWh
|
$2,608
-
MMBtu
|
|
10 | 2.7261: Install timers and/or thermostats | $14,474 | $50 |
$181
2,052
kWh
|
$14,293
-
MMBtu
|
|
TOTAL RECOMMENDED | $59,977 | $15,750 |
$29,567
335,874
kWh
|
$30,410
-
MMBtu
|
||
TOTAL IMPLEMENTED | $57,137 | $15,727 |
$29,335
333,236
kWh
|
$27,802
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs