ITAC Assessment: SD0196
ITAC logo
ITAC Assessment: SD0196
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Formed & Molded Plastic Products
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area 104,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $134,718 2,000,879
kWh
Electricity Demand $68,870 7,756
kW-mo/yr
Natural Gas $86,572 15,715
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $116,521 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,827

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $47,330 $12,960 $34,853
520,223
kWh
$13,808
-
kW-mo/yr
$(-1,331.0)
-
MMBtu
-
02 2.2511: Insulate bare equipment $4,292 $1,500 $3,074
46,014
kWh
$1,218
-
kW-mo/yr
- -
03 2.2515: Use optimum thickness insulation $3,308 $1,151 $2,369
35,463
kWh
$939
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $2,255 - $1,661
24,912
kWh
$594
-
kW-mo/yr
- -
05 2.4224: Upgrade controls on compressors $2,717 $5,000 $1,759
21,688
kWh
$958
-
kW-mo/yr
- -
06 2.2437: Recover waste heat from equipment $1,432 $1,305 $1,099
16,413
kWh
$333
-
kW-mo/yr
- -
07 2.7261: Install timers and/or thermostats $522 $600 $522
6,448
kWh
- - -
08 2.2442: Preheat combustion air with waste heat $7,420 $1,213 - - $7,420
-
MMBtu
-
09 2.6231: Utilize controls to operate equipment only when needed $1,836 $1,125 - - $1,836
-
MMBtu
-
10 2.1221: Replace obsolete burners with more efficient ones $1,339 $2,865 - - $1,339
-
MMBtu
-
11 2.7142: Utilize higher efficiency lamps and/or ballasts $2,972 $7,130 $2,049
30,481
kWh
$923
-
kW-mo/yr
- -
12 2.7144: Install spectral reflectors / delamp $3,025 $2,790 $2,022
30,188
kWh
$1,003
-
kW-mo/yr
- -
13 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,500 $8,500 - - - $3,500
14 3.7134: Wash and reuse rags on-site $1,598 $810 - - - $1,598
15 4.111: Add equipment/ operators to reduce production bottleneck $17,000 $3,500 - - - $17,000
16 4.423: Move product using mechanical means $11,475 $14,000 - - - $11,475
17 4.112: Replace old machine with new automatic multi-station tool $4,500 $1,000 - - - $4,500
TOTAL RECOMMENDED $116,521 $65,449 $49,408
731,830
kWh
$19,776
-
kW-mo/yr
$9,264
-
MMBtu
$38,073
TOTAL IMPLEMENTED $20,827 $19,281 $9,153
136,870
kWh
$3,674
-
kW-mo/yr
- $8,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs