| Assessment Year | 1992 |
|---|---|
| Principal Product | COMMERCIAL FOLDING BOXES |
| NAICS |
n/a
|
| SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
| Sales Range | $10 M to 50M |
| # of Employees | 137 |
| Plant Area |
n/a
|
| Annual Production | 250,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $182,715 | 1,981,536 |
kWh
|
$0.092 |
| Natural Gas | $46,022 | 8,237 |
MMBtu
|
$5.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,592 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6121: Reduce hot water temperature to the minimum required | $10,985 | $201 |
$10,985
119,285
kWh
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,401 | $68 |
$1,401
15,240
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,050 | $2,523 |
$3,416
37,222
kWh
|
- | $(-366.0) | |
| 04 | 2.3191: Use demand controller or load shedder | $10,165 | $2,500 |
$10,165
-
kWh
|
- | - | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $921 | $500 | - |
$921
-
MMBtu
|
- | |
| 06 | 2.7444: Close holes and openings in building such as broken windows | $14,070 | - | - |
$14,070
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $40,592 | $5,792 |
$25,967
171,747
kWh
|
$14,991
-
MMBtu
|
$(-366.0) | ||
| TOTAL IMPLEMENTED | $40,592 | $5,792 |
$25,967
171,747
kWh
|
$14,991
-
MMBtu
|
$(-366.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs