ITAC Assessment: MZ0085
ITAC logo
ITAC Assessment: MZ0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product zinc and plated fixtures
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 65
Plant Area 110,000
ft2
Annual Production 300
ton
Production Hrs. Annual 4,950
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,441 1,472,920
kWh
Electricity Demand $22,028 4,901
kW-mo/yr
Natural Gas $406,039 52,494
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $156,643 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $154,995

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,648 $820 $1,388
23,137
kWh
$260
-
kW-mo/yr
-
02 2.1131: Repair faulty insulation in furnaces, boilers, etc $79,573 $6,500 - - $79,573
-
MMBtu
03 2.1131: Repair faulty insulation in furnaces, boilers, etc $72,621 $8,500 - - $72,621
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,801 $8,200 $2,370
39,501
kWh
$431
-
kW-mo/yr
-
TOTAL RECOMMENDED $156,643 $24,020 $3,758
62,638
kWh
$691
-
kW-mo/yr
$152,194
-
MMBtu
TOTAL IMPLEMENTED $154,995 $23,200 $2,370
39,501
kWh
$431
-
kW-mo/yr
$152,194
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs