| Assessment Year | 1990 |
|---|---|
| Principal Product | FELT CARPET PADDING |
| NAICS |
n/a
|
| SIC | 2299: Textile goods, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 135 |
| Plant Area |
n/a
|
| Annual Production | 117,000
thousand feet
|
| Production Hrs. Annual | 3,760
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $585,765 | 7,021,981 |
kWh
|
$0.083 |
| Natural Gas | $293,580 | 41,806 |
MMBtu
|
$7.02 |
| Fuel Oil #2 | $4,073 | 630 |
MMBtu
|
$6.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $140,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,274 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $2,218 | $68 |
$2,218
26,671
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,495 | - |
$3,495
42,204
kWh
|
- | - | |
| 03 | 2.4312: Improve lubrication practices | $2,478 | $800 |
$2,478
29,894
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $602 | $86 |
$602
7,327
kWh
|
- | - | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,426 | $3,026 |
$6,426
77,374
kWh
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $2,454 | $6,245 |
$2,454
29,601
kWh
|
- | - | |
| 07 | 3.6122: Install solid waste incinerator for heat | $123,297 | $1,075,000 | - |
$119,224
-
MMBtu
|
$4,073
-
MMBtu
|
|
| TOTAL RECOMMENDED | $140,970 | $1,085,225 |
$17,673
213,071
kWh
|
$119,224
-
MMBtu
|
$4,073
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,274 | $6,399 |
$5,274
63,599
kWh
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs