Assessment Year | 1990 |
---|---|
Principal Product | FELT CARPET PADDING |
NAICS |
n/a
|
SIC | 2299: Textile goods, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
n/a
|
Annual Production | 117,000
thousand feet
|
Production Hrs. Annual | 3,760
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $585,765 | 7,021,981 |
kWh
|
$0.083 |
Natural Gas | $293,580 | 41,806 |
MMBtu
|
$7.02 |
Fuel Oil #2 | $4,073 | 630 |
MMBtu
|
$6.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $140,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,274 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $2,218 | $68 |
$2,218
26,671
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,495 | - |
$3,495
42,204
kWh
|
- | - | |
03 | 2.4312: Improve lubrication practices | $2,478 | $800 |
$2,478
29,894
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $602 | $86 |
$602
7,327
kWh
|
- | - | |
05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $6,426 | $3,026 |
$6,426
77,374
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $2,454 | $6,245 |
$2,454
29,601
kWh
|
- | - | |
07 | 3.6122: Install solid waste incinerator for heat | $123,297 | $1,075,000 | - |
$119,224
-
MMBtu
|
$4,073
-
MMBtu
|
|
TOTAL RECOMMENDED | $140,970 | $1,085,225 |
$17,673
213,071
kWh
|
$119,224
-
MMBtu
|
$4,073
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,274 | $6,399 |
$5,274
63,599
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs