| Assessment Year | 1990 |
|---|---|
| Principal Product | STEEL STRUCTURES |
| NAICS |
n/a
|
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 190 |
| Plant Area |
n/a
|
| Annual Production | 8,000
ton
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $293,307 | 2,783,998 |
kWh
|
$0.11 |
| Fuel Oil #2 | $68,005 | 16,380 |
MMBtu
|
$4.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,996 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,296 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $1,686 | $102 |
$1,686
15,240
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,408 | $650 |
$2,408
21,981
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,140 | $5,700 |
$2,140
19,343
kWh
|
- | |
| 04 | 2.7441: Replace broken windows and/or window sash | $5,202 | $450 | - |
$5,202
-
MMBtu
|
|
| 05 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $1,560 | $340 | - |
$1,560
-
MMBtu
|
|
| TOTAL RECOMMENDED | $12,996 | $7,242 |
$6,234
56,564
kWh
|
$6,762
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,296 | $1,202 |
$4,094
37,221
kWh
|
$5,202
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs