ITAC Assessment: MA0613
ITAC logo
ITAC Assessment: MA0613
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Printed circuit boards
NAICS 334412: Bare Printed Circuit Board Manufacturing
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 121
Plant Area 52,548
ft2
Annual Production 345,000
pieces
Production Hrs. Annual 4,550
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,785 1,653,504
kWh
Electricity Demand $52,787 5,662
kW-mo/yr
Electricity Fees $7,451 -
Paper $49,986 2,759
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,323 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,915

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Paper Savings
01 2.7314: Reduce ventilation air $22,488 $15,475 $7,543
69,200
kWh
$1,091
-
kW-mo/yr
$13,854
-
MMBtu
02 2.7232: Replace existing hvac unit with high efficiency model $15,346 $54,617 $15,088
138,427
kWh
$258
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,574 $53,250 $6,268
57,500
kWh
$1,306
-
kW-mo/yr
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $20,408 $15,900 $11,303
103,700
kWh
$1,770
-
kW-mo/yr
$7,335
-
MMBtu
05 2.2511: Insulate bare equipment $507 $256 - - $507
-
MMBtu
TOTAL RECOMMENDED $66,323 $139,498 $40,202
368,827
kWh
$4,425
-
kW-mo/yr
$21,696
-
MMBtu
TOTAL IMPLEMENTED $45,915 $123,598 $28,899
265,127
kWh
$2,655
-
kW-mo/yr
$14,361
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs