ITAC Assessment: RU0074
ITAC logo
ITAC Assessment: RU0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PAPER & PLASTIC BAGS
NAICS
n/a
SIC 2674: Uncoated Paper and Multiwall Bags
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area
n/a
Annual Production 18,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $232,582 2,790,739
kWh
Natural Gas $30,143 6,091
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,673 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $1,313 - $1,313
15,826
kWh
-
02 2.4312: Improve lubrication practices $1,790 $800 $1,790
21,688
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,155 $325 $2,155
26,084
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,206 $337 $4,206
47,773
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,419 $500 $8,419
101,407
kWh
-
06 2.7243: Improve air circulation with destratification fans / other methods $1,443 $4,860 $(-473.0)
(-5,569)
kWh
$1,916
-
MMBtu
08 2.7261: Install timers and/or thermostats $3,347 $2,390 - $3,347
-
MMBtu
TOTAL RECOMMENDED $22,673 $9,212 $17,410
207,209
kWh
$5,263
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs