ITAC Assessment: RU0024
ITAC logo
ITAC Assessment: RU0024
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product CUSTOM MOLDED PLASTICS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area
n/a
Annual Production 5,500,000
pieces
Production Hrs. Annual 5,880
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $229,216 2,585,580
kWh
Natural Gas $36,884 5,878
MMBtu
Fuel Oil #2 $11,783 2,758
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,265 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,853

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $870 $164 $870
9,672
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $417 $500 $417
4,689
kWh
-
03 2.7243: Improve air circulation with destratification fans / other methods $1,127 - $(-148.0)
(-1,758)
kWh
$1,275
-
MMBtu
04 2.2514: Cover open tanks $410 $200 - $410
-
MMBtu
05 2.4312: Improve lubrication practices $1,285 - $1,285
14,361
kWh
-
06 2.6231: Utilize controls to operate equipment only when needed $1,896 $1,650 $1,896
21,395
kWh
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,913 - $2,913
32,825
kWh
-
08 2.2136: Install / repair insulation on steam lines $397 $130 - $397
-
MMBtu
09 2.1233: Analyze flue gas for proper air/fuel ratio $1,950 $500 - $1,950
-
MMBtu
TOTAL RECOMMENDED $11,265 $3,144 $7,233
81,184
kWh
$4,032
-
MMBtu
TOTAL IMPLEMENTED $8,853 $3,144 $6,096
68,581
kWh
$2,757
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs