Assessment Year | 1988 |
---|---|
Principal Product | LASER TRIMMER SYSTEMS |
NAICS |
n/a
|
SIC | 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 540 |
Plant Area |
n/a
|
Annual Production | 80
pieces
|
Production Hrs. Annual | 2,100
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,711 | 4,162,661 |
kWh
|
$0.052 |
Natural Gas | $2,315 | 408 |
MMBtu
|
$5.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,947 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,958 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $1,607 | - |
$1,607
27,550
kWh
|
- | - | |
02 | 2.7261: Install timers and/or thermostats | $28,590 | $1,000 |
$27,154
522,274
kWh
|
$1,436
-
MMBtu
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $382 | $100 |
$382
7,327
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $2,666 | $3,230 |
$2,666
51,290
kWh
|
- | - | |
05 | 3.4115: Recover and reuse cooling water | $702 | $2,050 | - | - | $702 | |
TOTAL RECOMMENDED | $33,947 | $6,380 |
$31,809
608,441
kWh
|
$1,436
-
MMBtu
|
$702 | ||
TOTAL IMPLEMENTED | $31,958 | $6,280 |
$29,820
573,564
kWh
|
$1,436
-
MMBtu
|
$702 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs