Assessment Year | 2014 |
---|---|
Principal Product | Gray and Ductile iron |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
60,000
ft2
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $182,947 | 2,583,600 |
kWh
|
$0.071 |
Electricity Demand | $121,734 | 15,217 |
kW-mo/yr
|
$8.00 |
Natural Gas | $31,944 | 4,695 |
MMBtu
|
$6.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $124,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $97,789 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,989 | $700 |
$3,989
56,188
kWh
|
- | - | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $1,592 | $3,432 |
$1,592
22,426
kWh
|
- | - | - | |
03 | 2.2437: Recover waste heat from equipment | $891 | $847 | - | - |
$891
-
MMBtu
|
- | |
04 | 2.4227: Use compressor air filters | $721 | $112 |
$721
10,155
kWh
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,393 | - |
$2,393
33,711
kWh
|
- | - | - | |
06 | 2.4226: Use / purchase optimum sized compressor | $1,894 | $7,100 |
$1,894
26,670
kWh
|
- | - | - | |
07 | 2.7135: Install occupancy sensors | $3,196 | $1,170 |
$3,196
45,021
kWh
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,194 | $4,592 |
$1,194
16,810
kWh
|
- | - | - | |
09 | 2.7211: Clean and maintain refrigerant condensers and towers | $267 | $56 |
$224
3,154
kWh
|
$43
-
kW-mo/yr
|
- | - | |
10 | 2.7232: Replace existing hvac unit with high efficiency model | $840 | $910 |
$703
9,906
kWh
|
$136
-
kW-mo/yr
|
- | - | |
11 | 2.7261: Install timers and/or thermostats | $463 | $181 |
$225
3,172
kWh
|
- |
$238
-
MMBtu
|
- | |
12 | 2.6232: Install set-back timers | $6,977 | $3,900 | - | - |
$6,977
-
MMBtu
|
- | |
13 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,828 | $18,850 |
$10,828
152,501
kWh
|
- | - | - | |
14 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $381 | $1,728 |
$381
5,364
kWh
|
- | - | - | |
15 | 4.445: Install equipment to move product | $88,525 | $492,000 |
$8,686
122,340
kWh
|
$11,838
-
kW-mo/yr
|
- | $68,000 | |
TOTAL RECOMMENDED | $124,150 | $535,578 |
$36,026
507,418
kWh
|
$12,018
-
kW-mo/yr
|
$8,106
-
MMBtu
|
$68,000 | ||
TOTAL IMPLEMENTED | $97,789 | $499,968 |
$17,907
252,218
kWh
|
$11,882
-
kW-mo/yr
|
- | $68,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs