ITAC Assessment: AM0482
ITAC logo
ITAC Assessment: AM0482
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Carbonated beverages
NAICS 311930: Flavoring Syrup and Concentrate Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 120,000
ft2
Annual Production 7,200,000
pieces
Production Hrs. Annual 4,344
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $166,393 2,730,376
kWh
Electricity Demand $45,477 11,736
kW-mo/yr
Electricity Fees $897 -
Natural Gas $46,470 6,334
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,695 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,415

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings
01 3.4113: Treat and reuse rinse waters $50,000 $2,000 - - - $50,000
-
lb
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,940 $500 $4,800
81,000
kWh
$1,140
-
kW-mo/yr
- - -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,210 - $1,210
20,570
kWh
- - - -
04 2.4314: Use synthetic lubricant $1,020 - $800
13,550
kWh
$220
-
kW-mo/yr
- - -
05 2.7124: Make a practice of turning off lights when not needed $640 - $490
8,240
kWh
$150
-
kW-mo/yr
- - -
06 2.2511: Insulate bare equipment $280 $50 - - $280
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $605 $350 $130
2,210
kWh
$15
-
kW-mo/yr
- - $460
TOTAL RECOMMENDED $59,695 $2,900 $7,430
125,570
kWh
$1,525
-
kW-mo/yr
$280
-
MMBtu
$50,000
-
lb
$460
TOTAL IMPLEMENTED $59,415 $2,850 $7,430
125,570
kWh
$1,525
-
kW-mo/yr
- $50,000
-
lb
$460
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs