Assessment Year | 2005 |
---|---|
Principal Product | Carbonated beverages |
NAICS | 311930: Flavoring Syrup and Concentrate Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
120,000
ft2
|
Annual Production | 7,200,000
pieces
|
Production Hrs. Annual | 4,344
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $166,393 | 2,730,376 |
kWh
|
$0.061 |
Electricity Demand | $45,477 | 11,736 |
kW-mo/yr
|
$3.88 |
Electricity Fees | $897 | - |
|
- |
Natural Gas | $46,470 | 6,334 |
MMBtu
|
$7.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $59,695 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $59,415 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4113: Treat and reuse rinse waters | $50,000 | $2,000 | - | - | - |
$50,000
-
lb
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,940 | $500 |
$4,800
81,000
kWh
|
$1,140
-
kW-mo/yr
|
- | - | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,210 | - |
$1,210
20,570
kWh
|
- | - | - | - | |
04 | 2.4314: Use synthetic lubricant | $1,020 | - |
$800
13,550
kWh
|
$220
-
kW-mo/yr
|
- | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $640 | - |
$490
8,240
kWh
|
$150
-
kW-mo/yr
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $280 | $50 | - | - |
$280
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $605 | $350 |
$130
2,210
kWh
|
$15
-
kW-mo/yr
|
- | - | $460 | |
TOTAL RECOMMENDED | $59,695 | $2,900 |
$7,430
125,570
kWh
|
$1,525
-
kW-mo/yr
|
$280
-
MMBtu
|
$50,000
-
lb
|
$460 | ||
TOTAL IMPLEMENTED | $59,415 | $2,850 |
$7,430
125,570
kWh
|
$1,525
-
kW-mo/yr
|
- |
$50,000
-
lb
|
$460 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs