| Assessment Year | 1991 |
|---|---|
| Principal Product | TRUCKS |
| NAICS |
n/a
|
| SIC | 3533: Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 315 |
| Plant Area |
n/a
|
| Annual Production | 450
pieces
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $285,089 | 4,793,963 |
kWh
|
$0.059 |
| Natural Gas | $54,451 | 18,351 |
MMBtu
|
$2.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,312 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,312 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7123: Keep lamps and reflectors clean | $2,630 | - |
$2,477
41,618
kWh
|
- | $153 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $517 | $1,555 |
$517
8,792
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,136 | $9,186 |
$4,136
69,461
kWh
|
- | - | |
| 04 | 2.7261: Install timers and/or thermostats | $3,475 | $1,745 | - |
$3,475
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $1,411 | $1,150 |
$663
11,137
kWh
|
$748
-
MMBtu
|
- | |
| 06 | 2.6232: Install set-back timers | $7,481 | $3,386 |
$7,481
125,733
kWh
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,405 | - |
$4,705
79,132
kWh
|
- | $(-300.0) | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $10,257 | $50,625 |
$(-1,677.0)
(-28,136)
kWh
|
$11,934
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $34,312 | $67,647 |
$18,302
307,737
kWh
|
$16,157
-
MMBtu
|
$(-147.0) | ||
| TOTAL IMPLEMENTED | $34,312 | $67,647 |
$18,302
307,737
kWh
|
$16,157
-
MMBtu
|
$(-147.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs