| Assessment Year | 1989 |
|---|---|
| Principal Product | WOOLEN TEXTILES |
| NAICS |
n/a
|
| SIC | 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing) |
| Sales Range | $50 M to 100M |
| # of Employees | 320 |
| Plant Area |
n/a
|
| Annual Production | 51,840
thousand feet
|
| Production Hrs. Annual | 5,760
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $348,138 | 12,344,080 |
kWh
|
$0.028 |
| Natural Gas | $587,111 | 151,304 |
MMBtu
|
$3.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,591 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,808 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2163: Use minimum steam operating pressure | $7,313 | - | - |
$7,313
-
MMBtu
|
- | |
| 02 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $2,279 | $385 |
$1,531
80,598
kWh
|
- | $748 | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $18,329 | $5,500 | - |
$18,329
-
MMBtu
|
- | |
| 04 | 2.2121: Increase amount of condensate returned | $4,079 | $4,000 | - |
$3,960
-
MMBtu
|
$119 | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,207 | $1,800 |
$1,207
43,083
kWh
|
- | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,243 | $1,755 |
$1,243
43,962
kWh
|
- | - | |
| 07 | 2.2621: Modify refrigeration system to operate at a lower pressure | $6,141 | $14,400 |
$6,141
219,226
kWh
|
- | - | |
| TOTAL RECOMMENDED | $40,591 | $27,840 |
$10,122
386,869
kWh
|
$29,602
-
MMBtu
|
$867 | ||
| TOTAL IMPLEMENTED | $8,808 | $7,940 |
$3,981
167,643
kWh
|
$3,960
-
MMBtu
|
$867 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs