| Assessment Year | 1984 |
|---|---|
| Principal Product | SHOCK ABSORBERS |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 655 |
| Plant Area |
n/a
|
| Annual Production | 11,200,000
pieces
|
| Production Hrs. Annual | 0
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $733,458 | 16,864,889 |
kWh
|
$0.043 |
| Natural Gas | $196,256 | 40,389 |
MMBtu
|
$4.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,976 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,327 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2121: Increase amount of condensate returned | $614 | $450 | - |
$614
-
MMBtu
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,540 | $450 | - |
$2,600
-
MMBtu
|
$(-60.0) | |
| 03 | 2.7261: Install timers and/or thermostats | $1,020 | $600 | - |
$1,020
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $456 | $223 |
$456
14,947
kWh
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $1,279 | $82 |
$1,279
36,928
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $2,444 | $640 | - |
$2,444
-
MMBtu
|
- | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,630 | - |
$6,630
-
kWh
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $519 | $790 |
$519
11,430
kWh
|
- | - | |
| 09 | 2.3521: Reduce load on electrical conductor to reduce heating losses | $740 | $1,125 |
$740
17,585
kWh
|
- | - | |
| 10 | 2.2511: Insulate bare equipment | $900 | $46 | - |
$900
-
MMBtu
|
- | |
| 11 | 2.2121: Increase amount of condensate returned | $2,676 | $278 | - |
$2,676
-
MMBtu
|
- | |
| 12 | 2.2122: Install / repair insulation on condensate lines | $356 | $371 | - |
$356
-
MMBtu
|
- | |
| 13 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,802 | $200 | - |
$1,802
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $21,976 | $5,255 |
$9,624
80,890
kWh
|
$12,412
-
MMBtu
|
$(-60.0) | ||
| TOTAL IMPLEMENTED | $13,327 | $4,048 |
$975
26,377
kWh
|
$12,412
-
MMBtu
|
$(-60.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs