ITAC Assessment: OK0115
ITAC logo
ITAC Assessment: OK0115
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product SHOCK ABSORBERS
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 655
Plant Area
n/a
Annual Production 11,200,000
pieces
Production Hrs. Annual 0
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $733,458 16,864,889
kWh
Natural Gas $196,256 40,389
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,976 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,327

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2121: Increase amount of condensate returned $614 $450 - $614
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $2,540 $450 - $2,600
-
MMBtu
$(-60.0)
03 2.7261: Install timers and/or thermostats $1,020 $600 - $1,020
-
MMBtu
-
04 2.4221: Install compressor air intakes in coolest locations $456 $223 $456
14,947
kWh
- -
05 2.2511: Insulate bare equipment $1,279 $82 $1,279
36,928
kWh
- -
06 2.2511: Insulate bare equipment $2,444 $640 - $2,444
-
MMBtu
-
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $6,630 - $6,630
-
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $519 $790 $519
11,430
kWh
- -
09 2.3521: Reduce load on electrical conductor to reduce heating losses $740 $1,125 $740
17,585
kWh
- -
10 2.2511: Insulate bare equipment $900 $46 - $900
-
MMBtu
-
11 2.2121: Increase amount of condensate returned $2,676 $278 - $2,676
-
MMBtu
-
12 2.2122: Install / repair insulation on condensate lines $356 $371 - $356
-
MMBtu
-
13 2.7447: Install vinyl strip / high speed / air curtain doors $1,802 $200 - $1,802
-
MMBtu
-
TOTAL RECOMMENDED $21,976 $5,255 $9,624
80,890
kWh
$12,412
-
MMBtu
$(-60.0)
TOTAL IMPLEMENTED $13,327 $4,048 $975
26,377
kWh
$12,412
-
MMBtu
$(-60.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs