ITAC Assessment: OK0070
ITAC logo
ITAC Assessment: OK0070
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product PRINTED CATALOGS
NAICS
n/a
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area
n/a
Annual Production 17,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $282,297 7,745,604
kWh
Natural Gas $190,095 62,137
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,516

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,791 $60 $3,791
121,630
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $297 $392 $297
8,206
kWh
-
03 2.7261: Install timers and/or thermostats $163 $475 $163
4,396
kWh
-
04 2.7261: Install timers and/or thermostats $197 $475 - $197
-
MMBtu
05 2.6232: Install set-back timers $4,660 $14,963 $4,660
119,871
kWh
-
06 2.7231: Use radiant heater for spot heating $3,156 $1,000 - $3,156
-
MMBtu
07 2.3212: Optimize plant power factor $1,612 $2,173 $1,612
-
kWh
-
08 2.2414: Use waste heat from hot flue gases to preheat $9,064 $53,000 - $9,064
-
MMBtu
TOTAL RECOMMENDED $22,940 $72,538 $10,523
254,103
kWh
$12,417
-
MMBtu
TOTAL IMPLEMENTED $13,516 $18,588 $10,360
249,707
kWh
$3,156
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs