| Assessment Year | 1993 |
|---|---|
| Principal Product | Springs and Steel Stampings |
| NAICS |
n/a
|
| SIC | 3495: Wire Springs |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
400,000
ft2
|
| Annual Production | 7,600,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $323,717 | 6,250,293 |
kWh
|
$0.052 |
| Natural Gas | $242,673 | 91,304 |
MMBtu
|
$2.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,889 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,278 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $4,484 | $11,590 |
$4,484
86,753
kWh
|
- | |
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $16,677 | $9,940 | - |
$16,677
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $8,311 | $4,500 | - |
$8,311
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,926 | $500 |
$4,926
94,959
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $3,324 | $2,000 |
$3,324
64,185
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,041 | $1,171 |
$1,041
20,223
kWh
|
- | |
| 07 | 2.3212: Optimize plant power factor | $1,042 | $600 |
$1,042
-
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $84 | $120 |
$84
1,758
kWh
|
- | |
| TOTAL RECOMMENDED | $39,889 | $30,421 |
$14,901
267,878
kWh
|
$24,988
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $14,278 | $6,171 |
$5,967
115,182
kWh
|
$8,311
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs