| Assessment Year | 2014 |
|---|---|
| Principal Product | Concrete parts |
| NAICS | 327390: Other Concrete Product Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 48 |
| Plant Area |
50,000
ft2
|
| Annual Production | 81,000,000
lb
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $33,537 | 504,660 |
kWh
|
$0.066 |
| Electricity Demand | $10,091 | 2,439 |
kW-mo/yr
|
$4.14 |
| Natural Gas | $11,401 | 1,322 |
MMBtu
|
$8.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,355 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,283 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,354 | $28,643 |
$6,169
94,908
kWh
|
$1,572
-
kW-mo/yr
|
- | - | $613 | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $5,218 | $5,000 |
$4,291
66,021
kWh
|
$927
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $804 | $1,000 | - | - |
$804
-
MMBtu
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $359 | $650 |
$286
4,404
kWh
|
$73
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $327 | $50 |
$404
6,210
kWh
|
$103
-
kW-mo/yr
|
- | $(-100.0) | $(-80.0) | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $114 | $60 |
$57
873
kWh
|
$57
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $602 | $160 |
$278
4,275
kWh
|
$24
-
kW-mo/yr
|
- | - | $300 | |
| 08 | 2.7134: Use photocell controls | $211 | $40 |
$211
3,240
kWh
|
- | - | - | - | |
| 09 | 2.7135: Install occupancy sensors | $134 | $200 |
$134
2,063
kWh
|
- | - | - | - | |
| 10 | 2.4151: Develop a repair/replace policy | $1,232 | $4,256 |
$982
15,111
kWh
|
$250
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $17,355 | $40,059 |
$12,812
197,105
kWh
|
$3,006
-
kW-mo/yr
|
$804
-
MMBtu
|
$(-100.0) | $833 | ||
| TOTAL IMPLEMENTED | $9,283 | $28,853 |
$6,851
105,393
kWh
|
$1,699
-
kW-mo/yr
|
- | $(-100.0) | $833 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs