Assessment Year | 2013 |
---|---|
Principal Product | Tobacco |
NAICS | 312230: Tobacco Manufacturing |
SIC | 2141: Tobacco Stemming and Redrying |
Sales Range | $100 M to 500M |
# of Employees | 900 |
Plant Area |
725,000
ft2
|
Annual Production | 160,000,000
lb
|
Production Hrs. Annual | 3,360
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $841,050 | 12,350,400 |
kWh
|
$0.068 |
Electricity Demand | $211,571 | 43,266 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $11,154 | - |
|
- |
Natural Gas | $711,497 | 122,073 |
MMBtu
|
$5.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,572 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $51,293 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,444 | $4,038 |
$2,061
30,270
kWh
|
$420
-
kW-mo/yr
|
- | - | $(-37.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,134 | $10,830 |
$2,576
37,828
kWh
|
$558
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,033 | $1,068 |
$438
6,425
kWh
|
$43
-
kW-mo/yr
|
- | - | $552 | |
04 | 2.7135: Install occupancy sensors | $17,345 | $29,500 |
$17,345
254,701
kWh
|
- | - | - | - | |
05 | 2.7132: Install timers on light switches in little used areas | $141 | $110 |
$141
2,065
kWh
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $848 | $100 |
$1,403
20,606
kWh
|
$285
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,164 | $400 |
$1,763
25,895
kWh
|
$401
-
kW-mo/yr
|
- | - | - | |
08 | 2.2136: Install / repair insulation on steam lines | $2,106 | $4,672 | - | - |
$2,106
-
MMBtu
|
- | - | |
09 | 2.4151: Develop a repair/replace policy | $621 | $1,216 |
$494
7,253
kWh
|
$127
-
kW-mo/yr
|
- | - | - | |
10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,660 | $10,343 |
$5,300
77,835
kWh
|
$1,360
-
kW-mo/yr
|
- | - | - | |
11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $11,708 | $1,200 | - | - |
$11,708
-
MMBtu
|
- | - | |
12 | 2.1232: Keep boiler tubes clean | $17,500 | $10,000 | - | - |
$17,500
-
MMBtu
|
- | - | |
13 | 2.2113: Repair or replace steam traps | $758 | $5,500 | - | - |
$3,558
-
MMBtu
|
$(-400.0) | $(-2,400.0) | |
14 | 2.1241: Reduce excessive boiler blowdown | $4,110 | - | - | - |
$4,110
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $70,572 | $78,977 |
$31,521
462,878
kWh
|
$3,194
-
kW-mo/yr
|
$38,982
-
MMBtu
|
$(-1,000.0) | $(-2,125.0) | ||
TOTAL IMPLEMENTED | $51,293 | $57,130 |
$21,324
313,135
kWh
|
$843
-
kW-mo/yr
|
$32,766
-
MMBtu
|
$(-1,000.0) | $(-2,640.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs