ITAC Assessment: MI0464
ITAC logo
ITAC Assessment: MI0464
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Metal Sheets and Panels
NAICS 336411: Aircraft Manufacturing
SIC 3721: Aircraft
Sales Range $50
M
to 100
M
# of Employees 240
Plant Area 261,000
ft2
Annual Production 344,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $157,288 2,754,001
kWh
Electricity Demand $80,092 5,530
kW-mo/yr
Electricity Fees $60,177 -
TOTAL YEARLY COSTS $297,557
RECOMMENDED SAVINGS* $25,420 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7221: Lower temperature during the winter season and vice-versa $2,522 - $1,697
29,773
kWh
$825
-
kW-mo/yr
02 2.6231: Utilize controls to operate equipment only when needed $3,243 - $2,179
38,220
kWh
$1,064
-
kW-mo/yr
03 2.7444: Close holes and openings in building such as broken windows $5,173 $485 $3,479
61,030
kWh
$1,694
-
kW-mo/yr
04 2.7229: Air condition only space necessary $5,341 $960 $3,589
62,971
kWh
$1,752
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,193 $1,665 $4,832
84,770
kWh
$2,361
-
kW-mo/yr
06 2.6218: Turn off equipment when not in use $1,948 $2,600 $1,948
34,173
kWh
-
TOTAL RECOMMENDED $25,420 $5,710 $17,724
310,937
kWh
$7,696
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs