Assessment Year | 1996 |
---|---|
Principal Product | STEEL PRODUCTS |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
30,000
ft2
|
Annual Production | 1,500
pieces
|
Production Hrs. Annual | 4,992
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $86,560 | 822,392 |
kWh
|
$0.11 |
Electricity Demand | $25,131 | 3,042 |
kW-mo/yr
|
$8.26 |
Natural Gas | $17,298 | 2,780 |
MMBtu
|
$6.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,679 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,531 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $4,148 | $4,800 |
$4,148
59,496
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,679 | $600 |
$2,679
38,101
kWh
|
- | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,670 | $1,070 |
$2,863
41,032
kWh
|
$892
-
kW-mo/yr
|
$(-1,085.0)
-
MMBtu
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,594 | $1,530 | - | - |
$2,594
-
MMBtu
|
- | |
05 | 2.7261: Install timers and/or thermostats | $1,984 | $2,400 | - | - |
$1,984
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,191 | $4,542 |
$860
12,309
kWh
|
$331
-
kW-mo/yr
|
- | - | |
07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $848 | $200 | - | - |
$848
-
MMBtu
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $783 | $1,200 |
$783
11,137
kWh
|
- | - | - | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $782 | $10,247 | - | - | - |
$782
-
lb
|
|
TOTAL RECOMMENDED | $17,679 | $26,589 |
$11,333
162,075
kWh
|
$1,223
-
kW-mo/yr
|
$4,341
-
MMBtu
|
$782
-
lb
|
||
TOTAL IMPLEMENTED | $13,531 | $21,789 |
$7,185
102,579
kWh
|
$1,223
-
kW-mo/yr
|
$4,341
-
MMBtu
|
$782
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs