Assessment Year | 1992 |
---|---|
Principal Product | FABRICATED STEEL |
NAICS |
n/a
|
SIC | 3465: Automotive Stampings |
Sales Range | $10 M to 50M |
# of Employees | 210 |
Plant Area |
n/a
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 4,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $96,920 | 2,047,480 |
kWh
|
$0.047 |
LPG | $33,048 | 690,939 |
MMBtu
|
$0.048 |
Coal | $167,055 | 129,993 |
MMBtu
|
$1.29 |
Other Energy | $50,491 | 6,235 |
MMBtu
|
$8.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,318 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Energy Savings |
---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,803 | $150 |
$1,803
38,101
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,761 | - |
$1,761
37,222
kWh
|
- | |
03 | 2.8223: Add air shields to trucks to increase fuel mileage | $1,515 | - | - |
$1,515
-
MMBtu
|
|
04 | 2.7261: Install timers and/or thermostats | $888 | $645 |
$888
18,757
kWh
|
- | |
05 | 2.6232: Install set-back timers | $332 | $700 |
$332
7,034
kWh
|
- | |
TOTAL RECOMMENDED | $6,299 | $1,495 |
$4,784
101,114
kWh
|
$1,515
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,318 | $150 |
$1,803
38,101
kWh
|
$1,515
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs