| Assessment Year | 1992 |
|---|---|
| Principal Product | INDUS. CLEANING PRODUCTS |
| NAICS |
n/a
|
| SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
n/a
|
| Annual Production | 9,000
Tgal
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $42,534 | 604,924 |
kWh
|
$0.070 |
| Natural Gas | $20,533 | 4,790 |
MMBtu
|
$4.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $4,828 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,065 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7226: Use computer programs to optimize hvac performance | $1,475 | $6,000 | - |
$1,475
-
MMBtu
|
|
| 02 | 2.6212: Turn off equipment during breaks, reduce operating time | $701 | - |
$701
9,965
kWh
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $375 | $520 |
$(-41.0)
(-586)
kWh
|
$416
-
MMBtu
|
|
| 04 | 2.1232: Keep boiler tubes clean | $275 | $450 | - |
$275
-
MMBtu
|
|
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $408 | $480 | - |
$408
-
MMBtu
|
|
| 06 | 2.6232: Install set-back timers | $288 | $330 |
$288
4,103
kWh
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $474 | $350 |
$474
6,741
kWh
|
- | |
| 08 | 2.2437: Recover waste heat from equipment | $832 | $500 | - |
$832
-
MMBtu
|
|
| TOTAL RECOMMENDED | $4,828 | $8,630 |
$1,422
20,223
kWh
|
$3,406
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,065 | $2,300 |
$1,134
16,120
kWh
|
$1,931
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs