ITAC Assessment: KU0207
ITAC logo
ITAC Assessment: KU0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product LUBRICANTS & MAINTENANCE PRODUCTS
NAICS
n/a
SIC 2992: Lubricating Oils and Greases
Sales Range $10
M
to 50
M
# of Employees 147
Plant Area
n/a
Annual Production 50,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $268,979 5,039,859
kWh
Natural Gas $237,538 74,347
MMBtu
Other Energy $60,000 8,520
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $222,679 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,331

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
01 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $164,472 $840,000 $224,200
4,201,348
kWh
$(-59,728.0)
-
MMBtu
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $18,525 - $20,525
-
kWh
- - $(-2,000.0)
03 2.1233: Analyze flue gas for proper air/fuel ratio $9,480 - - $9,580
-
MMBtu
- $(-100.0)
04 2.6232: Install set-back timers $9,165 $1,494 $9,165
171,747
kWh
- - -
05 2.2414: Use waste heat from hot flue gases to preheat $6,099 $12,675 - $6,099
-
MMBtu
- -
06 2.1243: Use heat from boiler blowdown to preheat boiler feed water $5,637 $6,030 - $5,637
-
MMBtu
- -
07 2.7261: Install timers and/or thermostats $2,817 $52 $594
11,137
kWh
$2,223
-
MMBtu
- -
08 2.8223: Add air shields to trucks to increase fuel mileage $1,802 - - - $1,802
-
MMBtu
-
09 2.1233: Analyze flue gas for proper air/fuel ratio $1,433 - - $1,483
-
MMBtu
- $(-50.0)
10 2.2111: Install steam trap $600 $90 - $600
-
MMBtu
- -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $547 - $547
10,258
kWh
- - -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $516 $150 $516
9,672
kWh
- - -
13 2.6121: Reduce hot water temperature to the minimum required $469 - $469
8,792
kWh
- - -
14 2.4231: Reduce the pressure of compressed air to the minimum required $454 $20 $454
8,499
kWh
- - -
15 2.4221: Install compressor air intakes in coolest locations $375 $150 $375
7,034
kWh
- - -
16 2.2136: Install / repair insulation on steam lines $128 $100 - $128
-
MMBtu
- -
17 2.1131: Repair faulty insulation in furnaces, boilers, etc $160 $300 - $160
-
MMBtu
- -
TOTAL RECOMMENDED $222,679 $861,061 $256,845
4,428,487
kWh
$(-33,818.0)
-
MMBtu
$1,802
-
MMBtu
$(-2,150.0)
TOTAL IMPLEMENTED $49,331 $8,146 $32,270
220,105
kWh
$19,211
-
MMBtu
- $(-2,150.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs