ITAC Assessment: HO0232
ITAC logo
ITAC Assessment: HO0232
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Machine Services & Castings
NAICS
n/a
SIC 3399: Primary Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 70,000
ft2
Annual Production 370
ton
Production Hrs. Annual 6,120
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,671 3,342,321
kWh
Electricity Demand $96,687 11,501
kW-mo/yr
Electricity Fees $3,341 -
Natural Gas $47,996 6,786
MMBtu
LPG $37,253 6,695
MMBtu
Fuel Oil #2 $26,092 3,705
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $620,679 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,133

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $13,133 $35,343 $8,837
201,934
kWh
$4,296
-
kW-mo/yr
- - - -
02 2.7111: Reduce illumination to minimum necessary levels $6,004 - $6,004
130,129
kWh
- - - - -
03 2.7135: Install occupancy sensors $11,219 $2,000 $11,219
255,862
kWh
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $252 $600 $252
5,569
kWh
- - - - -
05 2.4227: Use compressor air filters $2,211 $150 $2,211
77,960
kWh
- - - - -
06 2.4221: Install compressor air intakes in coolest locations $1,237 $1,200 $832
17,585
kWh
$405
-
kW-mo/yr
- - - -
07 2.3511: Use plant owned transformers or lease transformers $18,455 $60,000 - - $18,455 - - -
08 2.3212: Optimize plant power factor $2,647 $4,134 - - $2,647 - - -
09 4.424: Improve space comfort conditioning $18,360 $8,000 - - - - - $18,360
10 4.513: Re-arrange equipment layout to reduce labor costs $61,200 $640 - - - - - $61,200
11 4.424: Improve space comfort conditioning $11,520 $724 - - - - - $11,520
12 4.611: Begin a practice of predictive / preventative maintenance $2,400 $1,035 - - - - - $2,400
13 4.611: Begin a practice of predictive / preventative maintenance $840 $25 - - - - - $840
14 4.521: Clear and rent existing space $341,986 $1,000 - - - - - $341,986
15 4.321: Optimize production lot sizes and inventories $7,800 $5,000 - - - - - $7,800
16 4.513: Re-arrange equipment layout to reduce labor costs $16,380 - - - - - - $16,380
17 3.7223: Install shrouding on machines to prevent splashing $2,295 $2,000 - - - - - $2,295
18 4.611: Begin a practice of predictive / preventative maintenance $1,500 $368 - - - - - $1,500
19 4.611: Begin a practice of predictive / preventative maintenance $5,360 $6,240 - - - - - $5,360
20 3.7311: Maintain machines to reduce leaks $2,280 $240 - - - $2,280
-
gal
- -
21 3.5311: Recover and reuse waste material $93,600 $500 - - - - $93,600
-
lb
-
TOTAL RECOMMENDED $620,679 $129,199 $29,355
689,039
kWh
$4,701
-
kW-mo/yr
$21,102 $2,280
-
gal
$93,600
-
lb
$469,641
TOTAL IMPLEMENTED $13,133 $35,343 $8,837
201,934
kWh
$4,296
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs