Assessment Year | 1985 |
---|---|
Principal Product | CEREAL ANIMAL FOOD |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $5 M to 10M |
# of Employees | 20 |
Plant Area |
n/a
|
Annual Production | 60,000
ton
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,804 | 858,148 |
kWh
|
$0.081 |
Natural Gas | $17,248 | 3,831 |
MMBtu
|
$4.50 |
Other Energy | $9,428 | 1,217 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,036 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $18,860 | - |
$21,590
265,533
kWh
|
- | - | $(-2,730.0) | |
02 | 2.3191: Use demand controller or load shedder | $7,380 | $3,000 |
$7,380
-
kWh
|
- | - | - | |
03 | 2.6232: Install set-back timers | $4,194 | $1,052 |
$4,194
51,583
kWh
|
- | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,813 | $500 |
$3,813
46,893
kWh
|
- | - | - | |
05 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $3,686 | $2,700 | - |
$3,686
-
MMBtu
|
- | - | |
06 | 2.1123: Install automatic stack damper | $1,854 | $700 | - |
$1,854
-
MMBtu
|
- | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $974 | - | - |
$1,274
-
MMBtu
|
- | $(-300.0) | |
08 | 2.7261: Install timers and/or thermostats | $2,887 | $1,200 |
$1,883
23,154
kWh
|
$1,004
-
MMBtu
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $739 | $100 |
$739
9,086
kWh
|
- | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $262 | $20 |
$262
3,224
kWh
|
- | - | - | |
11 | 2.8223: Add air shields to trucks to increase fuel mileage | $279 | - | - | - |
$279
-
MMBtu
|
- | |
12 | 2.2135: Repair and eliminate steam leaks | $108 | $50 | - |
$108
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $45,036 | $9,322 |
$39,861
399,473
kWh
|
$7,926
-
MMBtu
|
$279
-
MMBtu
|
$(-3,030.0) | ||
TOTAL IMPLEMENTED | $19,635 | $5,802 |
$17,270
121,630
kWh
|
$2,386
-
MMBtu
|
$279
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs