| Assessment Year | 1984 |
|---|---|
| Principal Product | ELEC. METER ENCLOSURES |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
n/a
|
| Annual Production | 8,000,000
lb
|
| Production Hrs. Annual | 3,600
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $137,462 | 2,079,133 |
kWh
|
$0.066 |
| Natural Gas | $76,391 | 15,629 |
MMBtu
|
$4.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $65,086 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $27,192 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $9,770 | $17,000 | - |
$9,770
-
MMBtu
|
|
| 02 | 2.7261: Install timers and/or thermostats | $9,768 | - |
$1,201
18,171
kWh
|
$8,567
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $194 | - |
$194
2,931
kWh
|
- | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $3,716 | $2,000 | - |
$3,716
-
MMBtu
|
|
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $7,516 | $2,774 |
$7,516
113,716
kWh
|
- | |
| 06 | 2.7141: Lower light fixtures in high ceiling areas | $2,809 | $3,750 |
$2,809
42,497
kWh
|
- | |
| 07 | 2.4312: Improve lubrication practices | $6,508 | $2,250 |
$6,508
98,476
kWh
|
- | |
| 08 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $4,591 | $7,800 |
$4,591
69,461
kWh
|
- | |
| 09 | 2.5195: Change product design to reduce energy requirements | $4,203 | $100 |
$4,203
63,599
kWh
|
- | |
| 10 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,389 | $5,000 | - |
$3,389
-
MMBtu
|
|
| 11 | 2.1123: Install automatic stack damper | $1,487 | $1,300 | - |
$1,487
-
MMBtu
|
|
| 13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,886 | $78 |
$2,886
43,669
kWh
|
- | |
| 14 | 2.4323: Use optimum size and capacity equipment | $1,763 | $3,100 |
$1,763
26,671
kWh
|
- | |
| 15 | 2.4312: Improve lubrication practices | $1,143 | $25 |
$1,143
17,292
kWh
|
- | |
| 16 | 2.4221: Install compressor air intakes in coolest locations | $659 | $125 |
$659
9,965
kWh
|
- | |
| 17 | 2.2414: Use waste heat from hot flue gases to preheat | $1,359 | $3,150 | - |
$1,359
-
MMBtu
|
|
| 18 | 2.2414: Use waste heat from hot flue gases to preheat | $1,061 | $1,400 | - |
$1,061
-
MMBtu
|
|
| 19 | 2.2223: Enhance sensitivity of temperature control and cutoff | $905 | $300 | - |
$905
-
MMBtu
|
|
| 20 | 2.6212: Turn off equipment during breaks, reduce operating time | $496 | $400 |
$310
4,689
kWh
|
$186
-
MMBtu
|
|
| 21 | 2.6121: Reduce hot water temperature to the minimum required | $495 | - | - |
$495
-
MMBtu
|
|
| 22 | 2.7444: Close holes and openings in building such as broken windows | $368 | $10 |
$368
5,569
kWh
|
- | |
| TOTAL RECOMMENDED | $65,086 | $50,562 |
$34,151
516,706
kWh
|
$30,935
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $27,192 | $10,588 |
$10,615
160,610
kWh
|
$16,577
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs