Assessment Year | 1984 |
---|---|
Principal Product | CEREALS |
NAICS |
n/a
|
SIC | 2041: Flour and Other Grain Mill Products |
Sales Range | $10 M to 50M |
# of Employees | 96 |
Plant Area |
n/a
|
Annual Production | 8,000,000
bushels
|
Production Hrs. Annual | 7,800
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $842,586 | 17,917,058 |
kWh
|
$0.047 |
Natural Gas | $510,956 | 145,330 |
MMBtu
|
$3.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $154,926 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $137,694 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $47,344 | $2,000 |
$47,344
-
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $36,100 | $1,000 |
$36,100
768,171
kWh
|
- | - | |
03 | 2.8114: Change rate schedules or other changes in utility service | $24,518 | $20,000 |
$24,518
-
kWh
|
- | - | |
04 | 2.3212: Optimize plant power factor | $18,864 | $28,500 |
$18,864
-
kWh
|
- | - | |
05 | 2.6232: Install set-back timers | $8,943 | $5,443 |
$8,943
191,090
kWh
|
- | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,298 | - | - |
$8,698
-
MMBtu
|
$(-400.0) | |
07 | 2.4221: Install compressor air intakes in coolest locations | $2,894 | $1,350 |
$2,894
61,547
kWh
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,750 | $20 |
$1,750
37,222
kWh
|
- | - | |
09 | 2.2163: Use minimum steam operating pressure | $3,645 | - | - |
$3,645
-
MMBtu
|
- | |
10 | 2.2511: Insulate bare equipment | $1,267 | $1,700 | - |
$1,267
-
MMBtu
|
- | |
11 | 2.7261: Install timers and/or thermostats | $1,116 | $300 |
$1,116
23,740
kWh
|
- | - | |
12 | 2.2135: Repair and eliminate steam leaks | $187 | $60 | - |
$187
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $154,926 | $60,373 |
$141,529
1,081,770
kWh
|
$13,797
-
MMBtu
|
$(-400.0) | ||
TOTAL IMPLEMENTED | $137,694 | $53,560 |
$127,942
791,911
kWh
|
$10,152
-
MMBtu
|
$(-400.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs