Assessment Year | 1984 |
---|---|
Principal Product | COMM. LIGHTING FIXTURES |
NAICS |
n/a
|
SIC | 3646: Commercial, Industrial, and Institutional Electric Lighting Fixtures |
Sales Range | $5 M to 10M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 125,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $28,759 | 282,532 |
kWh
|
$0.10 |
Natural Gas | $28,220 | 5,765 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,287 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,818 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $8,835 | - | - |
$8,835
-
MMBtu
|
- | |
02 | 2.7261: Install timers and/or thermostats | $376 | $200 |
$239
2,345
kWh
|
$137
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,383 | $2,250 |
$4,383
43,083
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $3,959 | $1,000 | - |
$3,959
-
MMBtu
|
- | |
05 | 2.2514: Cover open tanks | $2,396 | $4,000 | - |
$2,396
-
MMBtu
|
- | |
06 | 2.7441: Replace broken windows and/or window sash | $2,034 | $738 | - |
$2,034
-
MMBtu
|
- | |
07 | 2.2212: Use minimum safe oven ventilation | $474 | - |
$388
3,810
kWh
|
$1,436
-
MMBtu
|
$(-1,350.0) | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,132 | - | - |
$1,132
-
MMBtu
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $835 | $1,200 |
$835
8,206
kWh
|
- | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $447 | $215 |
$447
4,396
kWh
|
- | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $298 | $100 |
$298
2,931
kWh
|
- | - | |
12 | 2.6121: Reduce hot water temperature to the minimum required | $118 | - | - |
$118
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $25,287 | $9,703 |
$6,590
64,771
kWh
|
$20,047
-
MMBtu
|
$(-1,350.0) | ||
TOTAL IMPLEMENTED | $20,818 | $5,288 |
$5,904
58,030
kWh
|
$16,264
-
MMBtu
|
$(-1,350.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs