Assessment Year | 2016 |
---|---|
Principal Product | Aerospace Parts |
NAICS | 331523: Nonferrous Metal Die-Casting Foundries |
SIC | 3363: Aluminum Die-Castings |
Sales Range | $100 M to 500M |
# of Employees | 288 |
Plant Area |
162,437
ft2
|
Annual Production | 50,000
units
|
Production Hrs. Annual | 5,850
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $218,543 | 3,611,700 |
kWh
|
$0.061 |
Electricity Demand | $52,957 | 9,379 |
kW-mo/yr
|
$5.65 |
Electricity Fees | $21,623 | - |
|
- |
Natural Gas | $66,479 | 7,411 |
MMBtu
|
$8.97 |
TOTAL YEARLY COSTS | $359,602 | |||
RECOMMENDED SAVINGS* | $579,157 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,295 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Primary Raw Material Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.1161: Eliminate/reduce an operation | $357,967 | $669,217 |
$3,767
-
MMBtu
|
- | $(-1,000.0) | $355,200 | |
02 | 3.1193: Convert from batch operation to continuous processing | $190,362 | $300,000 | - | - | - | $190,362 | |
03 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $24,528 | $1,495 | - | $24,528 | - | - | |
04 | 2.5194: Redesign process | $4,005 | $3,500 |
$4,005
-
MMBtu
|
- | - | - | |
05 | 2.1113: Reduce combustion air flow to optimum | $2,295 | $1,000 |
$2,295
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $579,157 | $975,212 |
$10,067
-
MMBtu
|
$24,528 | $(-1,000.0) | $545,562 | ||
TOTAL IMPLEMENTED | $2,295 | $1,000 |
$2,295
-
MMBtu
|
- | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs