Assessment Year | 1983 |
---|---|
Principal Product | FLUORESCENT LIGHT FIXTURES |
NAICS |
n/a
|
SIC | 3645: Residential Electric Lighting Fixtures |
Sales Range | $5 M to 10M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 4,572
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,764 | 715,123 |
kWh
|
$0.075 |
Natural Gas | $46,392 | 9,495 |
MMBtu
|
$4.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,881 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,017 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2443: Re-use or recycle hot or cold process exhaust air | $12,636 | $13,000 | - |
$12,636
-
MMBtu
|
|
02 | 2.2443: Re-use or recycle hot or cold process exhaust air | $10,812 | $8,500 | - |
$10,812
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,389 | $4,629 |
$6,389
84,994
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,608 | $132 |
$3,608
48,066
kWh
|
- | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $2,533 | $2,500 |
$2,533
33,705
kWh
|
- | |
06 | 2.3212: Optimize plant power factor | $1,494 | $2,800 |
$1,494
-
kWh
|
- | |
07 | 2.7261: Install timers and/or thermostats | $727 | $200 |
$727
9,672
kWh
|
- | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,237 | $410 | - |
$1,237
-
MMBtu
|
|
09 | 2.1123: Install automatic stack damper | $1,110 | $2,589 | - |
$1,110
-
MMBtu
|
|
10 | 2.7447: Install vinyl strip / high speed / air curtain doors | $983 | $192 | - |
$983
-
MMBtu
|
|
11 | 2.4221: Install compressor air intakes in coolest locations | $352 | $100 |
$352
4,689
kWh
|
- | |
TOTAL RECOMMENDED | $41,881 | $35,052 |
$15,103
181,126
kWh
|
$26,778
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,017 | $3,623 |
$4,687
62,427
kWh
|
$3,330
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs