| Assessment Year | 1983 |
|---|---|
| Principal Product | TOOLS FOR CONCRETE |
| NAICS |
n/a
|
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $10 M to 50M |
| # of Employees | 151 |
| Plant Area |
n/a
|
| Annual Production | 7,000,000
lb
|
| Production Hrs. Annual | 4,175
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,230 | 2,307,444 |
kWh
|
$0.070 |
| Natural Gas | $45,164 | 8,375 |
MMBtu
|
$5.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,649 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,806 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Paper Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,313 | $35,000 |
$15,313
217,761
kWh
|
- | - | |
| 02 | 2.7444: Close holes and openings in building such as broken windows | $7,691 | $300 | - |
$7,691
-
MMBtu
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $5,773 | $3,300 | - |
$5,773
-
MMBtu
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $140 | $500 |
$140
2,052
kWh
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,642 | $750 |
$2,642
37,515
kWh
|
- | - | |
| 06 | 2.1123: Install automatic stack damper | $442 | $300 | - |
$442
-
MMBtu
|
- | |
| 07 | 2.1123: Install automatic stack damper | $3,591 | $4,600 | - |
$3,591
-
MMBtu
|
- | |
| 08 | 2.1231: Establish burner maintenance schedule for boilers | $4,043 | $1,440 | - |
$4,043
-
MMBtu
|
- | |
| 09 | 3.6121: Burn waste paper for heat | $16,658 | $58,000 | - |
$21,140
-
MMBtu
|
$(-4,482.0)
-
MMBtu
|
|
| 10 | 2.6121: Reduce hot water temperature to the minimum required | $356 | - | - |
$356
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $56,649 | $104,190 |
$18,095
257,328
kWh
|
$43,036
-
MMBtu
|
$(-4,482.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,806 | $8,200 | - |
$9,806
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Paper Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs