ITAC Assessment: KU0059
ITAC logo
ITAC Assessment: KU0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product CUSTOM STEEL FABRICATION
NAICS
n/a
SIC 3449: Miscellaneous Structural Metal Work
Sales Range $5
M
to 10
M
# of Employees 76
Plant Area
n/a
Annual Production 360
ton
Production Hrs. Annual 2,150
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,894 1,110,492
kWh
Natural Gas $45,899 12,253
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,504 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,284

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7442: Keep doors and windows shut when not on use $21,854 $500 - $21,854
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,516 $22,000 $5,516
113,716
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,363 $120 $4,363
89,977
kWh
-
04 2.7261: Install timers and/or thermostats $1,570 $250 $782
16,120
kWh
$788
-
MMBtu
05 2.6212: Turn off equipment during breaks, reduce operating time $1,405 $99 - $1,405
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $796 $139 $796
16,413
kWh
-
TOTAL RECOMMENDED $35,504 $23,108 $11,457
236,226
kWh
$24,047
-
MMBtu
TOTAL IMPLEMENTED $11,284 $22,219 $9,879
203,693
kWh
$1,405
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs