Assessment Year | 2005 |
---|---|
Principal Product | Bricks |
NAICS | 327120: Clay Building Material and Refractories Manufacturing |
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
120,000
ft2
|
Annual Production | 55,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $190,445 | 3,942,700 |
kWh
|
$0.048 |
Electricity Demand | $59,906 | 17,364 |
kW-mo/yr
|
$3.45 |
Electricity Fees | $5,696 | - |
|
- |
Natural Gas | $1,153,372 | 180,160 |
MMBtu
|
$6.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,716 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $20,281 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $8,544 | $1,824 | - | - |
$8,544
-
MMBtu
|
- | - | |
02 | 2.4151: Develop a repair/replace policy | $848 | $1,393 |
$664
15,285
kWh
|
$184
-
kW-mo/yr
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,259 | $379 |
$852
19,620
kWh
|
$407
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,022 | $100 |
$1,458
33,570
kWh
|
$464
-
kW-mo/yr
|
- | $(-600.0) | $(-300.0) | |
05 | 2.7124: Make a practice of turning off lights when not needed | $7,252 | $2,552 |
$7,252
166,925
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,356 | $660 |
$471
10,836
kWh
|
$53
-
kW-mo/yr
|
- | $847 | $(-15.0) | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $435 | $367 |
$390
8,985
kWh
|
$45
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $20,716 | $7,275 |
$11,087
255,221
kWh
|
$1,153
-
kW-mo/yr
|
$8,544
-
MMBtu
|
$247 | $(-315.0) | ||
TOTAL IMPLEMENTED | $20,281 | $6,908 |
$10,697
246,236
kWh
|
$1,108
-
kW-mo/yr
|
$8,544
-
MMBtu
|
$247 | $(-315.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs