| Assessment Year | 1981 |
|---|---|
| Principal Product | FLOUR,FARINA & FEED |
| NAICS |
n/a
|
| SIC | 2041: Flour and Other Grain Mill Products |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 226,000
lb
|
| Production Hrs. Annual | 6,792
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $335,328 | 9,117,527 |
kWh
|
$0.037 |
| Natural Gas | $19,870 | 7,014 |
MMBtu
|
$2.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,302 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $6,100 | $8,200 |
$6,100
-
kWh
|
- | |
| 02 | 2.6232: Install set-back timers | $15,466 | $16,824 |
$15,466
420,868
kWh
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $370 | $500 |
$370
10,258
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,128 | - |
$1,128
30,774
kWh
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $238 | $100 | - |
$238
-
MMBtu
|
|
| TOTAL RECOMMENDED | $23,302 | $25,624 |
$23,064
461,900
kWh
|
$238
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs