ITAC Assessment: KG0047
ITAC logo
ITAC Assessment: KG0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product processed meat
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 25,519
ft2
Annual Production 24,000,000
lb
Production Hrs. Annual 3,120
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,141 1,963,658
kWh
Electricity Demand $59,179 4,195
kW-mo/yr
Electricity Fees $706 -
Natural Gas $10,145 3,426
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,837 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $68,017

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
01 2.7111: Reduce illumination to minimum necessary levels $490 $430 $168
5,862
kWh
$322
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $6,320 $7,240 $2,627
92,321
kWh
$3,693
-
kW-mo/yr
- - - -
03 2.6242: Minimize operation of equipment maintained in standby condition $5,273 $150 - - $5,273
-
MMBtu
- - -
04 2.7442: Keep doors and windows shut when not on use $2,264 $800 $2,264
79,426
kWh
- - - - -
05 2.4314: Use synthetic lubricant $1,339 - $461
16,120
kWh
$878
-
kW-mo/yr
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $717 $129 $260
9,086
kWh
$457
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $470 $40 $148
5,275
kWh
$322
-
kW-mo/yr
- - - -
08 2.2511: Insulate bare equipment $934 $273 - - $934
-
MMBtu
- - -
09 2.7261: Install timers and/or thermostats $265 $150 $265
9,379
kWh
- - - - -
10 2.4221: Install compressor air intakes in coolest locations $79 $260 $79
879
kWh
- - - - -
11 3.1191: Change procedures / equipment / operating conditions $49,350 $13,000 - - - - - $49,350
12 3.5311: Recover and reuse waste material $9,606 $3,000 - - - - $9,606
-
lb
-
13 3.5311: Recover and reuse waste material $5,829 $1,000 - - - - $5,829
-
lb
-
14 3.4154: Eliminate leaks in water lines and valves $2,901 $150 - - - $2,901
-
Tgal
- -
TOTAL RECOMMENDED $85,837 $26,622 $6,272
218,348
kWh
$5,672
-
kW-mo/yr
$6,207
-
MMBtu
$2,901
-
Tgal
$15,435
-
lb
$49,350
TOTAL IMPLEMENTED $68,017 $15,639 $3,329
114,890
kWh
$1,335
-
kW-mo/yr
$5,273
-
MMBtu
$2,901
-
Tgal
$5,829
-
lb
$49,350
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs