Assessment Year | 1996 |
---|---|
Principal Product | processed meat |
NAICS |
n/a
|
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
25,519
ft2
|
Annual Production | 24,000,000
lb
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,141 | 1,963,658 |
kWh
|
$0.032 |
Electricity Demand | $59,179 | 4,195 |
kW-mo/yr
|
$14.11 |
Electricity Fees | $706 | - |
|
- |
Natural Gas | $10,145 | 3,426 |
MMBtu
|
$2.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $85,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,017 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $490 | $430 |
$168
5,862
kWh
|
$322
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $6,320 | $7,240 |
$2,627
92,321
kWh
|
$3,693
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.6242: Minimize operation of equipment maintained in standby condition | $5,273 | $150 | - | - |
$5,273
-
MMBtu
|
- | - | - | |
04 | 2.7442: Keep doors and windows shut when not on use | $2,264 | $800 |
$2,264
79,426
kWh
|
- | - | - | - | - | |
05 | 2.4314: Use synthetic lubricant | $1,339 | - |
$461
16,120
kWh
|
$878
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $717 | $129 |
$260
9,086
kWh
|
$457
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $470 | $40 |
$148
5,275
kWh
|
$322
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.2511: Insulate bare equipment | $934 | $273 | - | - |
$934
-
MMBtu
|
- | - | - | |
09 | 2.7261: Install timers and/or thermostats | $265 | $150 |
$265
9,379
kWh
|
- | - | - | - | - | |
10 | 2.4221: Install compressor air intakes in coolest locations | $79 | $260 |
$79
879
kWh
|
- | - | - | - | - | |
11 | 3.1191: Change procedures / equipment / operating conditions | $49,350 | $13,000 | - | - | - | - | - | $49,350 | |
12 | 3.5311: Recover and reuse waste material | $9,606 | $3,000 | - | - | - | - |
$9,606
-
lb
|
- | |
13 | 3.5311: Recover and reuse waste material | $5,829 | $1,000 | - | - | - | - |
$5,829
-
lb
|
- | |
14 | 3.4154: Eliminate leaks in water lines and valves | $2,901 | $150 | - | - | - |
$2,901
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $85,837 | $26,622 |
$6,272
218,348
kWh
|
$5,672
-
kW-mo/yr
|
$6,207
-
MMBtu
|
$2,901
-
Tgal
|
$15,435
-
lb
|
$49,350 | ||
TOTAL IMPLEMENTED | $68,017 | $15,639 |
$3,329
114,890
kWh
|
$1,335
-
kW-mo/yr
|
$5,273
-
MMBtu
|
$2,901
-
Tgal
|
$5,829
-
lb
|
$49,350 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs