Assessment Year | 2015 |
---|---|
Principal Product | Plastics |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
134,500
ft2
|
Annual Production | 1,500,000,000
pieces
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,233,839 | 11,371,830 |
kWh
|
$0.11 |
Electricity Demand | $159,563 | 21,134 |
kW-mo/yr
|
$7.55 |
Electricity Fees | $29,949 | - |
|
- |
Natural Gas | $64,867 | 5,270 |
MMBtu
|
$12.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $116,607 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,831 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4226: Use / purchase optimum sized compressor | $48,766 | $10,000 |
$44,416
411,260
kWh
|
$4,350
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $10,440 | - |
$9,564
88,560
kWh
|
$876
-
kW-mo/yr
|
- | |
03 | 2.2623: Minimize condenser cooling water temperature | $3,810 | $700 |
$3,810
35,320
kWh
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,618 | $30,804 |
$13,318
123,320
kWh
|
$1,300
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,334 | $9,600 |
$7,624
70,600
kWh
|
$710
-
kW-mo/yr
|
- | |
06 | 2.6232: Install set-back timers | $6,174 | $2,500 |
$5,629
52,125
kWh
|
$545
-
kW-mo/yr
|
- | |
07 | 2.7261: Install timers and/or thermostats | $3,560 | $300 |
$1,580
14,700
kWh
|
- |
$1,980
-
MMBtu
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,831 | $40,000 |
$3,216
29,780
kWh
|
$615
-
kW-mo/yr
|
- | |
09 | 2.2437: Recover waste heat from equipment | $17,074 | $64,980 | - | - |
$17,074
-
MMBtu
|
|
TOTAL RECOMMENDED | $116,607 | $158,884 |
$89,157
825,665
kWh
|
$8,396
-
kW-mo/yr
|
$19,054
-
MMBtu
|
||
TOTAL IMPLEMENTED | $17,831 | $40,300 |
$14,360
133,040
kWh
|
$1,491
-
kW-mo/yr
|
$1,980
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs